Utility Readiness
Data source: Supabase
| Utility/System | Total | Closed | Open | Blocked | Completion | Status |
|---|---|---|---|---|---|---|
| HVAC System | 7 | 0 | 7 | 7 | 9.3% | Blocked |
| Hydrogenation Area | 6 | 0 | 6 | 5 | 18.3% | Blocked |
| Hydrogen / Nitrogen Manifold | 5 | 0 | 5 | 5 | 5.0% | Blocked |
| Low Vacuum System | 4 | 0 | 4 | 4 | 6.3% | Blocked |
| Chilled Water Plant | 5 | 1 | 4 | 2 | 40.0% | Blocked |
| Chilled Brine Plant | 5 | 2 | 3 | 2 | 53.0% | Blocked |
| Scrubber System | 4 | 1 | 3 | 2 | 25.0% | Blocked |
| Hot Water System | 4 | 2 | 2 | 2 | 63.7% | Blocked |
| High Vacuum System | 4 | 2 | 2 | 2 | 57.5% | Blocked |
| Utility Manifold - SS Reactors | 3 | 1 | 2 | 1 | 33.3% | Blocked |
| Utility Manifold - GL Reactors | 3 | 1 | 2 | 1 | 33.3% | Blocked |
| Utility Manifold - Clean Room Reactors | 3 | 1 | 2 | 1 | 33.3% | Blocked |
| Hydrogen Reactor 250 L | 3 | 1 | 2 | 1 | 33.3% | Blocked |
| Cooling Towers | 2 | 0 | 2 | 0 | 55.0% | In Progress |