PP-0007: Complete reflux lines and interconnecting piping

Task Details

taskIdPP-0007
sourcePlant Head Email
workstreamEquipment
areaIntermediate
equipmentSystemSSR-201
capacitySize130
activityCategoryPiping
readinessGateMechanical Completion
activityDescriptionComplete reflux lines and interconnecting piping
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentVendor
responsiblePersonAmir Tanks
vendorAgencyAmir Tanks
targetCompletionDate2026-07-15
revisedTargetDate2026-07-22
actualCompletionDate
dependencyPredecessorFinal piping routing and vendor resource availability
blockertrue
blockingImpactedItemsReflux/distillation functional trial
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaReflux line, condenser, receiver, addition pot and azeotropic box connectivity verified.
remarksNextActionwaiting for Amir tanks team
lastUpdatedOn2026-07-14T05:33:13.426+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 5:33 AMUpdated by: SivaSource: Stakeholder update form

Remarks: waiting for Amir tanks team

Old values

owner department
Engineering
responsible person
remarks next action
revised target date
target completion date

New values

owner department
Vendor
responsible person
Amir Tanks
remarks next action
waiting for Amir tanks team
revised target date
2026-07-22
target completion date
2026-07-15