PP-0013: Complete vacuum connection to reactor

Task Details

taskIdPP-0013
sourceSheet2 transformed
workstreamUtility
areaIntermediate
equipmentSystemSSR-202
capacitySize130
activityCategoryPiping / Utility
readinessGateUtility Completion
activityDescriptionComplete vacuum connection to reactor
currentStatusPO Under Process
dashboardBucketProcurement Pending
priorityCritical
ownerDepartmentEngineering / Procurement
responsiblePerson
vendorAgencyVacuum / Piping Vendor
targetCompletionDate
revisedTargetDate
actualCompletionDate
dependencyPredecessorLow/high vacuum piping procurement and installation
blockertrue
blockingImpactedItemsSS reactor commissioning and vacuum hold test
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaVacuum line connected, tagged, leak-tested, and vacuum hold test recorded.
remarksNextActionOriginal sheet combines vacuum and scrubber connection.
lastUpdatedOn
updatedBy
daysToTarget
scheduleFlagBlocked
completionPercent0.2
criticalBlockerThemeVacuum

Stakeholder Task Update

Updates require DATA_SOURCE=supabase. CSV mode remains read-only.

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Update history is available when DATA_SOURCE=supabase is enabled. CSV mode remains read-only.