PP-0022: Complete vacuum connection to reactor

Task Details

taskIdPP-0022
sourceSheet2 transformed
workstreamUtility
areaIntermediate
equipmentSystemSSR-203
capacitySize250
activityCategoryPiping / Utility
readinessGateUtility Completion
activityDescriptionComplete vacuum connection to reactor
currentStatusMaterial Awaited
dashboardBucketProcurement Pending
priorityCritical
ownerDepartmentEngineering / Procurement
responsiblePersonMr.Sharma Ji
vendorAgencyVacuum / Piping Vendor
targetCompletionDate2026-07-30
revisedTargetDate
actualCompletionDate
dependencyPredecessorLow/high vacuum piping procurement and installation
blockertrue
blockingImpactedItemsSS reactor commissioning and vacuum hold test
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaVacuum line connected, tagged, leak-tested, and vacuum hold test recorded.
remarksNextActionwork to be started after receipt of material
lastUpdatedOn2026-07-16T06:10:58.328932+00:00
updatedByBackend bulk update / SSR-201 template propagation
daysToTarget
scheduleFlagBlocked
completionPercent0.3
criticalBlockerThemeVacuum

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 16, 2026, 6:10 AMUpdated by: Backend bulk update / SSR-201 template propagationSource: bulk ssr201 to ssr202 206 2026 07 15

Remarks: Backend propagation from manually updated SSR-201 equivalent task to save repeated data entry for SSR-202 to SSR-206.

Old values

blocker
Yes
priority
Critical
current status
PO Under Process
last updated on
updated by name
dashboard bucket
Procurement Pending
owner department
Engineering / Procurement
completion percent
0.2
responsible person
remarks next action
Original sheet combines vacuum and scrubber connection.
revised target date
target completion date

New values

blocker
Yes
priority
Critical
current status
Material Awaited
last updated on
2026-07-16T06:10:58.328932+00:00
updated by name
Backend bulk update / SSR-201 template propagation
dashboard bucket
Procurement Pending
owner department
Engineering / Procurement
template task id
57255bd3-431e-4e9f-a86c-fb8b81c25100
completion percent
0.3
responsible person
Mr.Sharma Ji
template task code
PP-0004
remarks next action
work to be started after receipt of material
revised target date
target completion date
2026-07-30