PP-0044: Execute equipment installation checklist and no-load commissioning trial

Task Details

taskIdPP-0044
sourceCommissioning Expert Addition
workstreamEquipment
areaIntermediate
equipmentSystemSSR-205
capacitySize500
activityCategoryCommissioning
readinessGateCommissioning
activityDescriptionExecute equipment installation checklist and no-load commissioning trial
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentEngineering / Production
responsiblePerson
vendorAgencyAmir Tanks
targetCompletionDate
revisedTargetDate
actualCompletionDate
dependencyPredecessorMechanical, utility, electrical, scrubber and vacuum readiness
blockertrue
blockingImpactedItemsSSR-205 qualification readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned commissioning checklist and trial run report.
remarksNextAction
lastUpdatedOn
updatedBy
daysToTarget
scheduleFlagBlocked
completionPercent0
criticalBlockerThemeVacuum

Stakeholder Task Update

Updates require DATA_SOURCE=supabase. CSV mode remains read-only.

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.