PP-0057: Complete vacuum connection to GLR

Task Details

taskIdPP-0057
sourceSheet2 transformed
workstreamUtility
areaIntermediate
equipmentSystemGLR-201
capacitySize100
activityCategoryPiping / Utility
readinessGateUtility Completion
activityDescriptionComplete vacuum connection to GLR
currentStatusMaterial Awaited
dashboardBucketProcurement Pending
priorityCritical
ownerDepartmentProcurement
responsiblePersonMr.Kailas
vendorAgencyVacuum / Piping Vendor
targetCompletionDate2026-07-25
revisedTargetDate
actualCompletionDate
dependencyPredecessorLow/high vacuum piping procurement and installation
blockertrue
blockingImpactedItemsGLR commissioning and vacuum hold test
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaVacuum line connected, tagged, leak-tested, and vacuum hold test recorded.
remarksNextActionwork to be started after receipt by 15/07/2026
lastUpdatedOn2026-07-14T05:52:11.794+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.3
criticalBlockerThemeVacuum

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 5:52 AMUpdated by: SivaSource: Stakeholder update form

Remarks: work to be started after receipt by 15/07/2026

Old values

current status
PO Under Process
owner department
Engineering / Procurement
responsible person
remarks next action
target completion date

New values

current status
Material Awaited
owner department
Procurement
responsible person
Mr.Kailas
remarks next action
work to be started after receipt by 15/07/2026
target completion date
2026-07-25