PP-0059: Complete hot water connection to GLR jacket / coil

Task Details

taskIdPP-0059
sourceSheet2 transformed
workstreamUtility
areaIntermediate
equipmentSystemGLR-201
capacitySize100
activityCategoryPiping / Utility
readinessGateUtility Completion
activityDescriptionComplete hot water connection to GLR jacket / coil
currentStatusClosed
dashboardBucketClosed
priorityCritical
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji
vendorAgencyAmir Tanks
targetCompletionDate
revisedTargetDate
actualCompletionDate
dependencyPredecessorHot water system installation and manifold readiness
blockertrue
blockingImpactedItemsGLR heating trial
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaHot water connection completed, leak-tested, circulation verified.
remarksNextActionInsulation under progress
lastUpdatedOn2026-07-14T05:57:19.585+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent1
criticalBlockerThemeHot Water

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 5:57 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Insulation under progress

Old values

current status
Not Started
responsible person
remarks next action

New values

current status
Closed
responsible person
Mr.Sharma Ji
remarks next action
Insulation under progress