PP-0065: Complete vacuum connection to GLR

Task Details

taskIdPP-0065
sourceSheet2 transformed
workstreamUtility
areaIntermediate
equipmentSystemGLR-202
capacitySize100
activityCategoryPiping / Utility
readinessGateUtility Completion
activityDescriptionComplete vacuum connection to GLR
currentStatusMaterial Awaited
dashboardBucketProcurement Pending
priorityCritical
ownerDepartmentProcurement
responsiblePersonMr.Kailas
vendorAgencyVacuum / Piping Vendor
targetCompletionDate2026-07-25
revisedTargetDate
actualCompletionDate
dependencyPredecessorLow/high vacuum piping procurement and installation
blockertrue
blockingImpactedItemsGLR commissioning and vacuum hold test
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaVacuum line connected, tagged, leak-tested, and vacuum hold test recorded.
remarksNextActionwork to be started after receipt by 15/07/2026
lastUpdatedOn2026-07-16T07:41:32.217168+00:00
updatedByBackend bulk update / GLR-201 template propagation
daysToTarget
scheduleFlagBlocked
completionPercent0.3
criticalBlockerThemeVacuum

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 16, 2026, 7:41 AMUpdated by: Backend bulk update / GLR-201 template propagationSource: bulk glr201 to glr202 205 2026 07 16

Remarks: Backend propagation from manually updated GLR-201 equivalent task to save repeated data entry for GLR-202 to GLR-205.

Old values

blocker
Yes
priority
Critical
current status
PO Under Process
last updated on
updated by name
dashboard bucket
Procurement Pending
owner department
Engineering / Procurement
completion percent
0.2
responsible person
remarks next action
revised target date
target completion date

New values

blocker
Yes
priority
Critical
current status
Material Awaited
last updated on
2026-07-16T07:41:32.217168+00:00
updated by name
Backend bulk update / GLR-201 template propagation
dashboard bucket
Procurement Pending
owner department
Procurement
template task id
258727a2-fd93-4506-9af4-aa58fa15f2b4
completion percent
0.3
responsible person
Mr.Kailas
template task code
PP-0057
remarks next action
work to be started after receipt by 15/07/2026
revised target date
target completion date
2026-07-25