PP-0066: Complete scrubber / vent connection to GLR

Task Details

taskIdPP-0066
sourceSheet2 transformed
workstreamSafety / EHS
areaIntermediate
equipmentSystemGLR-202
capacitySize100
activityCategoryPiping / Venting
readinessGateSafety Readiness
activityDescriptionComplete scrubber / vent connection to GLR
currentStatusReceived
dashboardBucketIn Progress
priorityCritical
ownerDepartmentVendor
responsiblePersonMr.Reji (Vendor)
vendorAgencyScrubber / Piping Vendor
targetCompletionDate2026-07-25
revisedTargetDate
actualCompletionDate
dependencyPredecessorScrubber piping fabrication and header connection
blockertrue
blockingImpactedItemsSafe GLR trial and vent handling readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaScrubber/vent line connected, leak-tested, flow path verified.
remarksNextActionwork to be started from 15/07/2026
lastUpdatedOn2026-07-16T07:41:32.217168+00:00
updatedByBackend bulk update / GLR-201 template propagation
daysToTarget
scheduleFlagBlocked
completionPercent0.5
criticalBlockerThemeScrubber

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 16, 2026, 7:41 AMUpdated by: Backend bulk update / GLR-201 template propagationSource: bulk glr201 to glr202 205 2026 07 16

Remarks: Backend propagation from manually updated GLR-201 equivalent task to save repeated data entry for GLR-202 to GLR-205.

Old values

blocker
Yes
priority
Critical
current status
PO Under Process
last updated on
updated by name
dashboard bucket
Procurement Pending
owner department
Engineering / Procurement
completion percent
0.2
responsible person
remarks next action
revised target date
target completion date

New values

blocker
Yes
priority
Critical
current status
Received
last updated on
2026-07-16T07:41:32.217168+00:00
updated by name
Backend bulk update / GLR-201 template propagation
dashboard bucket
In Progress
owner department
Vendor
template task id
8d18ef0e-19bb-46e2-a306-7704788a6fa5
completion percent
0.5
responsible person
Mr.Reji (Vendor)
template task code
PP-0058
remarks next action
work to be started from 15/07/2026
revised target date
target completion date
2026-07-25