Pilot Plant TrackerChecking session…
← Back to Master Task RegisterDashboard

Data source: Supabase

PP-0069: Execute GLR installation checklist and no-load commissioning trial

Task Details

taskIdPP-0069
sourceCommissioning Expert Addition
workstreamEquipment
areaIntermediate
equipmentSystemGLR-202
capacitySize100
activityCategoryCommissioning
readinessGateCommissioning
activityDescriptionExecute GLR installation checklist and no-load commissioning trial
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentVendor
responsiblePersonHLE Glass Coat (Vendor)
vendorAgencyGLR Vendor
targetCompletionDate2026-08-05
revisedTargetDate
actualCompletionDate
dependencyPredecessorBottom valve, condenser, utilities, vacuum, scrubber and electrical readiness
blockertrue
blockingImpactedItemsGLR-202 qualification readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned commissioning checklist and trial run report.
remarksNextActionwaiting for completion of utility and other activities
lastUpdatedOn2026-07-16T07:41:32.217168+00:00
updatedByBackend bulk update / GLR-201 template propagation
daysToTarget
scheduleFlagBlocked
completionPercent0
criticalBlockerThemeVacuum

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 16, 2026, 7:41 AMUpdated by: Backend bulk update / GLR-201 template propagationSource: bulk glr201 to glr202 205 2026 07 16

Remarks: Backend propagation from manually updated GLR-201 equivalent task to save repeated data entry for GLR-202 to GLR-205.

Old values

blocker
Yes
priority
Critical
current status
Not Started
last updated on
updated by name
dashboard bucket
Not Started
owner department
Engineering / Production
completion percent
0
responsible person
remarks next action
revised target date
target completion date

New values

blocker
Yes
priority
Critical
current status
Not Started
last updated on
2026-07-16T07:41:32.217168+00:00
updated by name
Backend bulk update / GLR-201 template propagation
dashboard bucket
Not Started
owner department
Vendor
template task id
3a204593-7b05-48d7-8e04-8573a3023de8
completion percent
0
responsible person
HLE Glass Coat (Vendor)
template task code
PP-0061
remarks next action
waiting for completion of utility and other activities
revised target date
target completion date
2026-08-05