PP-0075: Complete hot water connection to GLR jacket / coil

Task Details

taskIdPP-0075
sourceSheet2 transformed
workstreamUtility
areaIntermediate
equipmentSystemGLR-203
capacitySize250
activityCategoryPiping / Utility
readinessGateUtility Completion
activityDescriptionComplete hot water connection to GLR jacket / coil
currentStatusClosed
dashboardBucketClosed
priorityCritical
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji
vendorAgencyAmir Tanks
targetCompletionDate
revisedTargetDate
actualCompletionDate
dependencyPredecessorHot water system installation and manifold readiness
blockertrue
blockingImpactedItemsGLR heating trial
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaHot water connection completed, leak-tested, circulation verified.
remarksNextActionInsulation under progress
lastUpdatedOn2026-07-16T07:41:32.217168+00:00
updatedByBackend bulk update / GLR-201 template propagation
daysToTarget
scheduleFlagBlocked
completionPercent1
criticalBlockerThemeHot Water

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 16, 2026, 7:41 AMUpdated by: Backend bulk update / GLR-201 template propagationSource: bulk glr201 to glr202 205 2026 07 16

Remarks: Backend propagation from manually updated GLR-201 equivalent task to save repeated data entry for GLR-202 to GLR-205.

Old values

blocker
Yes
priority
Critical
current status
Not Started
last updated on
updated by name
dashboard bucket
Not Started
owner department
Engineering
completion percent
0
responsible person
remarks next action
revised target date
target completion date

New values

blocker
Yes
priority
Critical
current status
Closed
last updated on
2026-07-16T07:41:32.217168+00:00
updated by name
Backend bulk update / GLR-201 template propagation
dashboard bucket
Closed
owner department
Engineering
template task id
0fbcdb6c-efac-43d8-b887-5f19e4da0943
completion percent
1
responsible person
Mr.Sharma Ji
template task code
PP-0059
remarks next action
Insulation under progress
revised target date
target completion date