PP-0079: Receive and install glass-lined reactor in final position

Task Details

taskIdPP-0079
sourcePlant Head Email
workstreamEquipment
areaIntermediate
equipmentSystemGLR-204
capacitySize250
activityCategoryMechanical
readinessGateMechanical Completion
activityDescriptionReceive and install glass-lined reactor in final position
currentStatusClosed
dashboardBucketClosed
priorityHigh
ownerDepartmentEngineering
responsiblePerson
vendorAgencyGLR Vendor
targetCompletionDate
revisedTargetDate
actualCompletionDate2026-07-03
dependencyPredecessor
blockerfalse
blockingImpactedItems
commissioningImpactfalse
qualificationImpactfalse
evidenceAcceptanceCriteriaInstalled in position and verified against layout.
remarksNextActionStatus captured from Plant Head email dated 03-Jul-2026.
lastUpdatedOn2026-07-16T07:41:32.217168+00:00
updatedByBackend bulk update / GLR-201 template propagation
daysToTarget0
scheduleFlagClosed
completionPercent1
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 16, 2026, 7:41 AMUpdated by: Backend bulk update / GLR-201 template propagationSource: bulk glr201 to glr202 205 2026 07 16

Remarks: Backend propagation from manually updated GLR-201 equivalent task to save repeated data entry for GLR-202 to GLR-205.

Old values

blocker
No
priority
High
current status
Closed
last updated on
updated by name
dashboard bucket
Closed
owner department
Engineering
completion percent
1
responsible person
remarks next action
Status captured from Plant Head email dated 03-Jul-2026.
revised target date
target completion date

New values

blocker
No
priority
High
current status
Closed
last updated on
2026-07-16T07:41:32.217168+00:00
updated by name
Backend bulk update / GLR-201 template propagation
dashboard bucket
Closed
owner department
Engineering
template task id
3575954d-4d5a-4bf0-9534-b8880cd98ab8
completion percent
1
responsible person
template task code
PP-0055
remarks next action
Status captured from Plant Head email dated 03-Jul-2026.
revised target date
target completion date