PP-0088: Fix and verify GLR bottom valve

Task Details

taskIdPP-0088
sourceSheet2 transformed
workstreamEquipment
areaClean room
equipmentSystemGLR-205
capacitySize250
activityCategoryMechanical
readinessGateMechanical Completion
activityDescriptionFix and verify GLR bottom valve
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji
vendorAgencyAmir Tanks / GLR Vendor
targetCompletionDate2026-07-25
revisedTargetDate
actualCompletionDate
dependencyPredecessorBottom valve and vendor availability
blockertrue
blockingImpactedItemsGLR-205 mechanical completion and trial operation
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaBottom valve installed, leak-tight, accessible, and tagged.
remarksNextActionReceived, to be installed
lastUpdatedOn2026-07-16T07:41:32.217168+00:00
updatedByBackend bulk update / GLR-201 template propagation
daysToTarget19
scheduleFlagBlocked
completionPercent0.55
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 16, 2026, 7:41 AMUpdated by: Backend bulk update / GLR-201 template propagationSource: bulk glr201 to glr202 205 2026 07 16

Remarks: Backend propagation from manually updated GLR-201 equivalent task to save repeated data entry for GLR-202 to GLR-205.

Old values

blocker
Yes
priority
Critical
current status
Not Started
last updated on
updated by name
dashboard bucket
Not Started
owner department
Engineering
completion percent
0
responsible person
remarks next action
Target captured from source sheet: 22-Jul-2026.
revised target date
target completion date
2026-07-22

New values

blocker
Yes
priority
Critical
current status
Work In Progress
last updated on
2026-07-16T07:41:32.217168+00:00
updated by name
Backend bulk update / GLR-201 template propagation
dashboard bucket
In Progress
owner department
Engineering
template task id
0b88174d-9075-4d7e-8de0-904d99e69378
completion percent
0.55
responsible person
Mr.Sharma Ji
template task code
PP-0056
remarks next action
Received, to be installed
revised target date
target completion date
2026-07-25