PP-0096: Complete VTD room civil work: doors, AHU, air pipelines and flooring

Task Details

taskIdPP-0096
sourceSheet2 transformed
workstreamArea
areaClean room
equipmentSystemVTD-202
capacitySize12 trays
activityCategoryCivil / HVAC
readinessGateArea Readiness
activityDescriptionComplete VTD room civil work: doors, AHU, air pipelines and flooring
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentEngineering / HVAC
responsiblePersonPradham HVAC
vendorAgencyCivil / HVAC Vendor
targetCompletionDate2026-08-14
revisedTargetDate
actualCompletionDate
dependencyPredecessorCivil access and HVAC work completion
blockertrue
blockingImpactedItemsVTD-202 installation and commissioning
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaRoom completed and released for equipment installation.
remarksNextAction
lastUpdatedOn2026-07-29T04:58:52.121+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerThemeHVAC

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 29, 2026, 4:58 AMUpdated by: SivaSource: Stakeholder update form

Remarks: work under progress

Old values

responsible person
target completion date

New values

responsible person
Pradham HVAC
target completion date
2026-08-14