PP-0097: Complete hot water connection to VTD

Task Details

taskIdPP-0097
sourceSheet2 transformed
workstreamUtility
areaClean room
equipmentSystemVTD-202
capacitySize12 trays
activityCategoryPiping / Utility
readinessGateUtility Completion
activityDescriptionComplete hot water connection to VTD
currentStatusClosed
dashboardBucketClosed
priorityCritical
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji / Vendor
vendorAgencyAmir Tanks / Utility Vendor
targetCompletionDate2026-07-25
revisedTargetDate
actualCompletionDate
dependencyPredecessorHot water system installation and manifold readiness
blockertrue
blockingImpactedItemsVTD-202 heating trial
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaHot water connection completed, leak-tested and circulation verified.
remarksNextAction
lastUpdatedOn2026-07-29T06:49:03.067+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent1
criticalBlockerThemeHot Water

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 29, 2026, 6:49 AMUpdated by: SivaSource: Stakeholder update form

Remarks: completed

Old values

current status
Not Started
responsible person
target completion date

New values

current status
Closed
responsible person
Mr.Sharma Ji / Vendor
target completion date
2026-07-25