PP-0100: Verify VTD motor rotation, control panel, earthing, interlocks and instruments

Task Details

taskIdPP-0100
sourceCommissioning Expert Addition
workstreamElectrical / Instrumentation
areaClean room
equipmentSystemVTD-202
capacitySize12 trays
activityCategoryElectrical / Instrumentation
readinessGateElectrical / Instrumentation
activityDescriptionVerify VTD motor rotation, control panel, earthing, interlocks and instruments
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentElectrical / Instrumentation
responsiblePersonMr.Sharma
vendorAgencyE&I Vendor
targetCompletionDate2026-08-31
revisedTargetDate
actualCompletionDate
dependencyPredecessorMain electrical supply and control panel readiness
blockertrue
blockingImpactedItemsVTD-202 safe trial
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned E&I checklist, calibration records and interlock test sheet.
remarksNextAction
lastUpdatedOn2026-07-29T06:53:54.854+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 29, 2026, 6:53 AMUpdated by: SivaSource: Stakeholder update form

Remarks: completed

Old values

responsible person
target completion date

New values

responsible person
Mr.Sharma
target completion date
2026-08-31