PP-0106: Complete vacuum connection to VTD
Task Details
| taskId | PP-0106 |
|---|---|
| source | Sheet2 transformed |
| workstream | Utility |
| area | Intermediate |
| equipmentSystem | VTD-201 |
| capacitySize | 24 trays |
| activityCategory | Vacuum |
| readinessGate | Utility Completion |
| activityDescription | Complete vacuum connection to VTD |
| currentStatus | PO Under Process |
| dashboardBucket | Procurement Pending |
| priority | Critical |
| ownerDepartment | Engineering / Procurement |
| responsiblePerson | |
| vendorAgency | Vacuum / Piping Vendor |
| targetCompletionDate | |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Low/high vacuum piping procurement and installation |
| blocker | true |
| blockingImpactedItems | VTD-201 vacuum drying trial |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Vacuum line connected and vacuum hold test completed. |
| remarksNextAction | |
| lastUpdatedOn | |
| updatedBy | |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 0.2 |
| criticalBlockerTheme | Vacuum |
Stakeholder Task Update
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Blocked By / Upstream Tasks
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
Blocking / Downstream Tasks
No downstream task dependencies are mapped for this task.
Recent Update History
No update history has been recorded for this task yet.