PP-0108: Verify VTD motor rotation, control panel, earthing, interlocks and instruments

Task Details

taskIdPP-0108
sourceCommissioning Expert Addition
workstreamElectrical / Instrumentation
areaIntermediate
equipmentSystemVTD-201
capacitySize24 trays
activityCategoryElectrical / Instrumentation
readinessGateElectrical / Instrumentation
activityDescriptionVerify VTD motor rotation, control panel, earthing, interlocks and instruments
currentStatusNot Started
dashboardBucketNot Started
priorityCritical
ownerDepartmentElectrical / Instrumentation
responsiblePersonMr.Sharma Ji
vendorAgencyE&I Vendor
targetCompletionDate2026-08-31
revisedTargetDate
actualCompletionDate
dependencyPredecessorMain electrical supply and control panel readiness
blockertrue
blockingImpactedItemsVTD-201 safe trial
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaSigned E&I checklist, calibration records and interlock test sheet.
remarksNextActionAfter completion of all connections
lastUpdatedOn2026-07-29T06:45:01.855+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 29, 2026, 6:45 AMUpdated by: SivaSource: Stakeholder update form

Remarks: After completion of all works

Old values

responsible person
remarks next action
target completion date

New values

responsible person
Mr.Sharma Ji
remarks next action
After completion of all connections
target completion date
2026-08-31