PP-0110: Prepare and execute IQ/OQ package for VTD

Task Details

taskIdPP-0110
sourceCommissioning Expert Addition
workstreamQualification
areaIntermediate
equipmentSystemVTD-201
capacitySize24 trays
activityCategoryQualification
readinessGateQualification
activityDescriptionPrepare and execute IQ/OQ package for VTD
currentStatusNot Started
dashboardBucketNot Started
priorityHigh
ownerDepartmentQA / Validation
responsiblePersonMr.Sharma Ji / Mr.Jain Ji
vendorAgency
targetCompletionDate2026-09-30
revisedTargetDate
actualCompletionDate
dependencyPredecessorCommissioning checklist, calibration certificates and SOPs
blockertrue
blockingImpactedItems
commissioningImpactfalse
qualificationImpacttrue
evidenceAcceptanceCriteriaApproved IQ/OQ report and QA release.
remarksNextAction
lastUpdatedOn2026-07-29T06:47:10.455+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 29, 2026, 6:47 AMUpdated by: SivaSource: Stakeholder update form

Remarks: work to be started

Old values

blocker
No
responsible person
target completion date

New values

blocker
Yes
responsible person
Mr.Sharma Ji / Mr.Jain Ji
target completion date
2026-09-30