PP-0111: Complete doors and area access readiness

Task Details

taskIdPP-0111
sourceSheet2 transformed
workstreamArea
areaClean room
equipmentSystemWashing area
capacitySize
activityCategoryCivil
readinessGateArea Readiness
activityDescriptionComplete doors and area access readiness
currentStatusWork In Progress
dashboardBucketIn Progress
priorityHigh
ownerDepartmentEngineering
responsiblePersonMr.Sharma
vendorAgencyCivil / HVAC Vendor
targetCompletionDate2026-08-31
revisedTargetDate
actualCompletionDate
dependencyPredecessor
blockerfalse
blockingImpactedItemsClean room area readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaCompleted work with site verification and sign-off.
remarksNextAction
lastUpdatedOn2026-07-29T04:52:05.343+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0.55
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 29, 2026, 4:52 AMUpdated by: SivaSource: Stakeholder update form

Remarks: work under progress

Old values

current status
Not Started
responsible person
target completion date

New values

current status
Work In Progress
responsible person
Mr.Sharma
target completion date
2026-08-31