Remarks: work under progress
Old values
- current status
- Not Started
- responsible person
- —
- target completion date
- —
New values
- current status
- Work In Progress
- responsible person
- Pradham HVAC
- target completion date
- 2026-08-31
Data source: Supabase
| taskId | PP-0112 |
|---|---|
| source | Sheet2 transformed |
| workstream | HVAC / Clean Room |
| area | Clean room |
| equipmentSystem | Washing area |
| capacitySize | |
| activityCategory | HVAC |
| readinessGate | Area Readiness |
| activityDescription | Complete AHU installation / connection for washing area |
| currentStatus | Work In Progress |
| dashboardBucket | In Progress |
| priority | High |
| ownerDepartment | Engineering / HVAC |
| responsiblePerson | Pradham HVAC |
| vendorAgency | HVAC Vendor |
| targetCompletionDate | 2026-08-31 |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | HVAC completion |
| blocker | true |
| blockingImpactedItems | HVAC readiness |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Completed work with site verification and sign-off. |
| remarksNextAction | |
| lastUpdatedOn | 2026-07-29T04:54:14.589+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 0.55 |
| criticalBlockerTheme | HVAC |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: work under progress