PP-0115: Complete doors and area access readiness

Task Details

taskIdPP-0115
sourceSheet2 transformed
workstreamArea
areaClean room
equipmentSystemPackaging area
capacitySize
activityCategoryCivil
readinessGateArea Readiness
activityDescriptionComplete doors and area access readiness
currentStatusWork In Progress
dashboardBucketIn Progress
priorityHigh
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji / Vendor
vendorAgencyCivil Vendor
targetCompletionDate2026-08-31
revisedTargetDate
actualCompletionDate
dependencyPredecessor
blockerfalse
blockingImpactedItemsPackaging area readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaCompleted work with site verification and sign-off.
remarksNextActionwork under progress
lastUpdatedOn2026-07-24T05:33:08.353+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0.55
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 24, 2026, 5:33 AMUpdated by: SivaSource: Stakeholder update form

Remarks: work under progress

Old values

current status
Not Started
responsible person
remarks next action
target completion date

New values

current status
Work In Progress
responsible person
Mr.Sharma Ji / Vendor
remarks next action
work under progress
target completion date
2026-08-31