PP-0116: Complete AHU installation / connection for packaging area

Task Details

taskIdPP-0116
sourceSheet2 transformed
workstreamHVAC / Clean Room
areaClean room
equipmentSystemPackaging area
capacitySize
activityCategoryHVAC
readinessGateArea Readiness
activityDescriptionComplete AHU installation / connection for packaging area
currentStatusWork In Progress
dashboardBucketIn Progress
priorityHigh
ownerDepartmentEngineering / HVAC
responsiblePersonPradham HVAC
vendorAgencyHVAC Vendor
targetCompletionDate2026-08-31
revisedTargetDate
actualCompletionDate
dependencyPredecessorHVAC completion
blockertrue
blockingImpactedItemsHVAC readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaCompleted work with site verification and sign-off.
remarksNextActionwork under progress
lastUpdatedOn2026-07-24T05:34:53.316+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerThemeHVAC

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 24, 2026, 5:34 AMUpdated by: SivaSource: Stakeholder update form

Remarks: work under progress

Old values

current status
Not Started
responsible person
remarks next action
target completion date

New values

current status
Work In Progress
responsible person
Pradham HVAC
remarks next action
work under progress
target completion date
2026-08-31