PP-0119: Install multi-mill

Task Details

taskIdPP-0119
sourceSheet2 transformed
workstreamEquipment
areaIntermediate
equipmentSystemMilling and sifting area
capacitySize
activityCategoryMechanical
readinessGateMechanical Completion
activityDescriptionInstall multi-mill
currentStatusNot Started
dashboardBucketNot Started
priorityHigh
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji / Mr.Jain Ji
vendorAgencyEquipment Vendor
targetCompletionDate2026-08-31
revisedTargetDate
actualCompletionDate
dependencyPredecessor
blockerfalse
blockingImpactedItemsMilling readiness
commissioningImpactfalse
qualificationImpactfalse
evidenceAcceptanceCriteriaCompleted work with site verification and sign-off.
remarksNextActionMulti Mill received, Intermediate area by 31/08/2026, PP Area completed documentation to be started
lastUpdatedOn2026-07-23T04:35:58.944+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 23, 2026, 4:35 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Multi Mill received, to be installed

Old values

responsible person
remarks next action
target completion date

New values

responsible person
Mr.Sharma Ji / Mr.Jain Ji
remarks next action
Multi Mill received, Intermediate area by 31/08/2026, PP Area completed documentation to be started
target completion date
2026-08-31