PP-0123: Complete dust extraction / dusting connections

Task Details

taskIdPP-0123
sourceSheet2 transformed
workstreamSafety / EHS
areaIntermediate
equipmentSystemMilling and sifting area
capacitySize
activityCategoryDust Control
readinessGateSafety Readiness
activityDescriptionComplete dust extraction / dusting connections
currentStatusClosed
dashboardBucketClosed
priorityCritical
ownerDepartmentPlant Head
responsiblePersonMr.Siva
vendorAgencyDusting / HVAC Vendor
targetCompletionDate2026-07-23
revisedTargetDate
actualCompletionDate
dependencyPredecessorHVAC completion
blockertrue
blockingImpactedItemsDust control and clean operation
commissioningImpacttrue
qualificationImpactfalse
evidenceAcceptanceCriteriaCompleted work with site verification and sign-off.
remarksNextActionNot applicable
lastUpdatedOn2026-07-23T04:47:38.473+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent1
criticalBlockerThemeHVAC

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 23, 2026, 4:47 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Not possible to arrange duct collecting system

Old values

current status
Under Discussion
owner department
Engineering / EHS
responsible person
remarks next action
target completion date

New values

current status
Closed
owner department
Plant Head
responsible person
Mr.Siva
remarks next action
Not applicable
target completion date
2026-07-23