PP-0124: Fix doors and windows

Task Details

taskIdPP-0124
sourceSheet2 transformed
workstreamArea
areaIntermediate
equipmentSystemIntermediate storage area
capacitySize
activityCategoryCivil
readinessGateArea Readiness
activityDescriptionFix doors and windows
currentStatusWork In Progress
dashboardBucketIn Progress
priorityHigh
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji / JIT
vendorAgencyCivil Vendor
targetCompletionDate2026-08-10
revisedTargetDate
actualCompletionDate
dependencyPredecessor
blockerfalse
blockingImpactedItemsStorage area readiness
commissioningImpacttrue
qualificationImpactfalse
evidenceAcceptanceCriteriaCompleted work with site verification and sign-off.
remarksNextActionDoor fixing completed except double doors, awaited for windows material
lastUpdatedOn2026-07-17T11:43:00.469+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0.55
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 17, 2026, 11:43 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Door fixing completed except double doors, awaited for windows material

Old values

responsible person
remarks next action
target completion date

New values

responsible person
Mr.Sharma Ji / JIT
remarks next action
Door fixing completed except double doors, awaited for windows material
target completion date
2026-08-10