Remarks: Door to be fixed
Old values
- responsible person
- —
- target completion date
- —
New values
- responsible person
- Mr.Sharma
- target completion date
- 2026-08-31
Data source: Supabase
| taskId | PP-0127 |
|---|---|
| source | Sheet2 transformed |
| workstream | Area |
| area | Intermediate |
| equipmentSystem | Raw material storage area |
| capacitySize | |
| activityCategory | Civil |
| readinessGate | Area Readiness |
| activityDescription | Fix doors and windows |
| currentStatus | Work In Progress |
| dashboardBucket | In Progress |
| priority | High |
| ownerDepartment | Engineering |
| responsiblePerson | Mr.Sharma |
| vendorAgency | Civil Vendor |
| targetCompletionDate | 2026-08-31 |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | |
| blocker | false |
| blockingImpactedItems | Storage area readiness |
| commissioningImpact | true |
| qualificationImpact | false |
| evidenceAcceptanceCriteria | Completed work with site verification and sign-off. |
| remarksNextAction | |
| lastUpdatedOn | 2026-07-27T11:23:48.854+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | No Target |
| completionPercent | 0.55 |
| criticalBlockerTheme |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: Door to be fixed