Remarks: completed
Old values
- responsible person
- —
New values
- responsible person
- Mr.Sharma Ji
Data source: Supabase
| taskId | PP-0129 |
|---|---|
| source | Sheet2 transformed |
| workstream | Safety / EHS |
| area | Intermediate |
| equipmentSystem | Mezzanine floor |
| capacitySize | |
| activityCategory | Access / Safety |
| readinessGate | Safety Readiness |
| activityDescription | Complete man movement pathway |
| currentStatus | Closed |
| dashboardBucket | Closed |
| priority | Critical |
| ownerDepartment | Engineering / EHS |
| responsiblePerson | Mr.Sharma Ji |
| vendorAgency | Amir Tanks / Fabrication Vendor |
| targetCompletionDate | |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | |
| blocker | false |
| blockingImpactedItems | Safe access for commissioning |
| commissioningImpact | true |
| qualificationImpact | false |
| evidenceAcceptanceCriteria | Completed work with site verification and sign-off. |
| remarksNextAction | |
| lastUpdatedOn | 2026-07-23T04:30:54.282+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | No Target |
| completionPercent | 1 |
| criticalBlockerTheme | Platform / Access |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: completed
Remarks: work completed