PP-0130: Complete ladders for man movement

Task Details

taskIdPP-0130
sourceSheet2 transformed
workstreamSafety / EHS
areaIntermediate
equipmentSystemMezzanine floor
capacitySize
activityCategoryAccess / Safety
readinessGateSafety Readiness
activityDescriptionComplete ladders for man movement
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentEngineering / EHS
responsiblePersonMr.Sharma Ji / Vendor
vendorAgencyAmir Tanks / Fabrication Vendor
targetCompletionDate2026-08-14
revisedTargetDate
actualCompletionDate
dependencyPredecessor
blockerfalse
blockingImpactedItemsSafe access for operation
commissioningImpacttrue
qualificationImpactfalse
evidenceAcceptanceCriteriaCompleted work with site verification and sign-off.
remarksNextActionwork under progress
lastUpdatedOn2026-07-23T04:32:11.489+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0.55
criticalBlockerThemePlatform / Access

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 23, 2026, 4:32 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Intermediate area completed, clean room under progress, emergency exit to be started

Old values

responsible person
remarks next action
target completion date

New values

responsible person
Mr.Sharma Ji / Vendor
remarks next action
work under progress
target completion date
2026-08-14