PP-0131: Install emergency exit doors

Task Details

taskIdPP-0131
sourceSheet2 transformed
workstreamSafety / EHS
areaIntermediate
equipmentSystemEmergency exit
capacitySize
activityCategoryEmergency / EHS
readinessGateSafety Readiness
activityDescriptionInstall emergency exit doors
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentEngineering / EHS
responsiblePerson
vendorAgencyCivil Vendor
targetCompletionDate2026-08-15
revisedTargetDate
actualCompletionDate
dependencyPredecessor
blockerfalse
blockingImpactedItemsEmergency evacuation readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaCompleted work with site verification and sign-off.
remarksNextActioncan be installed after completion of work
lastUpdatedOn2026-07-14T09:57:44.318+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerThemeEmergency / EHS

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 9:57 AMUpdated by: SivaSource: Stakeholder update form

Remarks: can be installed after completion of work

Old values

blocker
Yes
remarks next action
target completion date

New values

blocker
No
remarks next action
can be installed after completion of work
target completion date
2026-08-15