Remarks: can be installed after completion of work
Old values
- blocker
- Yes
- remarks next action
- —
- target completion date
- —
New values
- blocker
- No
- remarks next action
- can be installed after completion of work
- target completion date
- 2026-08-15
Data source: Supabase
| taskId | PP-0131 |
|---|---|
| source | Sheet2 transformed |
| workstream | Safety / EHS |
| area | Intermediate |
| equipmentSystem | Emergency exit |
| capacitySize | |
| activityCategory | Emergency / EHS |
| readinessGate | Safety Readiness |
| activityDescription | Install emergency exit doors |
| currentStatus | Work In Progress |
| dashboardBucket | In Progress |
| priority | Critical |
| ownerDepartment | Engineering / EHS |
| responsiblePerson | |
| vendorAgency | Civil Vendor |
| targetCompletionDate | 2026-08-15 |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | |
| blocker | false |
| blockingImpactedItems | Emergency evacuation readiness |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Completed work with site verification and sign-off. |
| remarksNextAction | can be installed after completion of work |
| lastUpdatedOn | 2026-07-14T09:57:44.318+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 0.55 |
| criticalBlockerTheme | Emergency / EHS |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: can be installed after completion of work