PP-0132: Finalize emergency exit location

Task Details

taskIdPP-0132
sourceSheet2 transformed
workstreamSafety / EHS
areaClean room
equipmentSystemEmergency exit
capacitySize
activityCategoryEmergency / EHS
readinessGateSafety Readiness
activityDescriptionFinalize emergency exit location
currentStatusUnder Discussion
dashboardBucketNot Started
priorityCritical
ownerDepartmentEngineering / EHS
responsiblePersonSiva
vendorAgencyEngineering / EHS
targetCompletionDate2026-07-20
revisedTargetDate
actualCompletionDate
dependencyPredecessor
blockertrue
blockingImpactedItemsClean room evacuation readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaCompleted work with site verification and sign-off.
remarksNextActionIdentified one of the area, to be finalized
lastUpdatedOn2026-07-14T09:56:31.518+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.05
criticalBlockerThemeEmergency / EHS

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 9:56 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Identified one of the area, to be finalized

Old values

responsible person
remarks next action
target completion date

New values

responsible person
Siva
remarks next action
Identified one of the area, to be finalized
target completion date
2026-07-20