PP-0133: Install and commission fire alarm system

Task Details

taskIdPP-0133
sourceSheet2 transformed
workstreamSafety / EHS
areaPilot plant
equipmentSystemFire alarm system
capacitySize
activityCategoryFire / Alarm
readinessGateSafety Readiness
activityDescriptionInstall and commission fire alarm system
currentStatusMaterial Awaited
dashboardBucketProcurement Pending
priorityCritical
ownerDepartmentSafety / EHS
responsiblePersonMr.Vishal
vendorAgencyFire Alarm Vendor
targetCompletionDate2026-08-05
revisedTargetDate
actualCompletionDate
dependencyPredecessorFire alarm vendor mobilization and cabling readiness
blockertrue
blockingImpactedItemsPlant operational safety clearance
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaFire alarm installation, testing and EHS sign-off.
remarksNextActionwork to be started end of July 2026
lastUpdatedOn2026-07-14T10:01:03.708+00:00
updatedBySiva
daysToTarget22
scheduleFlagBlocked
completionPercent0.3
criticalBlockerThemeEmergency / EHS

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 10:01 AMUpdated by: SivaSource: Stakeholder update form

Remarks: work to be started end of July 2026

Old values

current status
Not Started
owner department
EHS / Electrical
responsible person
remarks next action
Target captured from Excel serial date 46228 = 25-Jul-2026.
target completion date
2026-07-25

New values

current status
Material Awaited
owner department
Safety / EHS
responsible person
Mr.Vishal
remarks next action
work to be started end of July 2026
target completion date
2026-08-05