PP-0135: Verify chilled water plant received, installed and positioned

Task Details

taskIdPP-0135
sourcePlant Head Email
workstreamUtility
areaUtility Yard / Pilot Plant
equipmentSystemChilled Water Plant
capacitySize
activityCategoryMechanical / Utility
readinessGateMechanical Completion
activityDescriptionVerify chilled water plant received, installed and positioned
currentStatusClosed
dashboardBucketClosed
priorityHigh
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji / Vendor
vendorAgencyUtility Vendor
targetCompletionDate
revisedTargetDate
actualCompletionDate2026-07-03
dependencyPredecessor
blockerfalse
blockingImpactedItems
commissioningImpactfalse
qualificationImpactfalse
evidenceAcceptanceCriteriaInstalled in position.
remarksNextAction
lastUpdatedOn2026-07-29T09:10:17.596+00:00
updatedBySiva
daysToTarget0
scheduleFlagClosed
completionPercent1
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 29, 2026, 9:10 AMUpdated by: SivaSource: Stakeholder update form

Remarks: completed

Old values

responsible person

New values

responsible person
Mr.Sharma Ji / Vendor