PP-0139: Perform temperature achievement, circulation and load verification for chilled water plant

Task Details

taskIdPP-0139
sourceCommissioning Expert Addition
workstreamUtility
areaUtility Yard / Pilot Plant
equipmentSystemChilled Water Plant
capacitySize
activityCategoryPerformance Test
readinessGateCommissioning
activityDescriptionPerform temperature achievement, circulation and load verification for chilled water plant
currentStatusUnder Discussion
dashboardBucketNot Started
priorityHigh
ownerDepartmentVendor
responsiblePersonMr.Sukla
vendorAgencyUtility Vendor
targetCompletionDate2026-07-25
revisedTargetDate
actualCompletionDate
dependencyPredecessorChilled Water Plant commissioning completion
blockertrue
blockingImpactedItems
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaPerformance trial report and utility handover.
remarksNextActionScheduled in next week
lastUpdatedOn2026-07-17T10:53:44.629+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0.05
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 17, 2026, 10:53 AMUpdated by: SivaSource: Stakeholder update form

Remarks: After completion of commissioning, testing can be performed

Old values

current status
Not Started

New values

current status
Under Discussion
Jul 17, 2026, 10:50 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Scheduled in next week

Old values

blocker
No
owner department
Engineering / Utility
responsible person
remarks next action
target completion date

New values

blocker
Yes
owner department
Vendor
responsible person
Mr.Sukla
remarks next action
Scheduled in next week
target completion date
2026-07-25