PP-0142: Complete insulation for chilled brine plant piping and headers

Task Details

taskIdPP-0142
sourceSheet1 priority
workstreamUtility
areaUtility Yard / Pilot Plant
equipmentSystemChilled Brine Plant
capacitySize
activityCategoryInsulation
readinessGateUtility Completion
activityDescriptionComplete insulation for chilled brine plant piping and headers
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentVendor
responsiblePersonRavi Insulations
vendorAgencyInsulation Vendor
targetCompletionDate2026-07-30
revisedTargetDate
actualCompletionDate
dependencyPredecessorInsulation PO release and vendor mobilization
blockertrue
blockingImpactedItemsChilled Brine Plant commissioning and reactor utility availability
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaInsulation completed and inspected.
remarksNextActionwork under progress
lastUpdatedOn2026-07-14T09:31:29.214+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerThemeInsulation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 9:31 AMUpdated by: SivaSource: Stakeholder update form

Remarks: work under progress

Old values

current status
PO Under Process
owner department
Engineering / Procurement
responsible person
remarks next action
target completion date

New values

current status
Work In Progress
owner department
Vendor
responsible person
Ravi Insulations
remarks next action
work under progress
target completion date
2026-07-30