PP-0143: Commission chilled brine plant after insulation completion

Task Details

taskIdPP-0143
sourcePlant Head Email
workstreamUtility
areaUtility Yard / Pilot Plant
equipmentSystemChilled Brine Plant
capacitySize
activityCategoryCommissioning
readinessGateCommissioning
activityDescriptionCommission chilled brine plant after insulation completion
currentStatusUnder Discussion
dashboardBucketNot Started
priorityCritical
ownerDepartmentVendor
responsiblePersonCooling people
vendorAgencyUtility Vendor
targetCompletionDate2026-07-21
revisedTargetDate
actualCompletionDate
dependencyPredecessorChilled Brine Plant insulation completion
blockertrue
blockingImpactedItemsGLR / SSR / condenser / clean room commissioning readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaCommissioning report with flow, temperature and load trial results.
remarksNextActioninformed to vendor, date to be confirmed
lastUpdatedOn2026-07-14T09:35:50.85+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.05
criticalBlockerThemeInsulation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 9:35 AMUpdated by: SivaSource: Stakeholder update form

Remarks: informed to vendor, date to be confirmed

Old values

current status
Not Started
owner department
Engineering / Utility
responsible person
remarks next action
target completion date

New values

current status
Under Discussion
owner department
Vendor
responsible person
Cooling people
remarks next action
informed to vendor, date to be confirmed
target completion date
2026-07-21