PP-0144: Perform temperature achievement, circulation and load verification for chilled brine plant

Task Details

taskIdPP-0144
sourceCommissioning Expert Addition
workstreamUtility
areaUtility Yard / Pilot Plant
equipmentSystemChilled Brine Plant
capacitySize
activityCategoryPerformance Test
readinessGateCommissioning
activityDescriptionPerform temperature achievement, circulation and load verification for chilled brine plant
currentStatusUnder Discussion
dashboardBucketNot Started
priorityHigh
ownerDepartmentVendor
responsiblePersonCooling people
vendorAgencyUtility Vendor
targetCompletionDate2026-07-21
revisedTargetDate
actualCompletionDate
dependencyPredecessorChilled Brine Plant commissioning completion
blockerfalse
blockingImpactedItems
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaPerformance trial report and utility handover.
remarksNextActiondate to be confirmed by vendor
lastUpdatedOn2026-07-14T09:37:52.42+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0.05
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 9:37 AMUpdated by: SivaSource: Stakeholder update form

Remarks: date to be confirmed by vendor

Old values

current status
Not Started
owner department
Engineering / Utility
responsible person
remarks next action
target completion date

New values

current status
Under Discussion
owner department
Vendor
responsible person
Cooling people
remarks next action
date to be confirmed by vendor
target completion date
2026-07-21