Remarks: work under progress
Old values
- current status
- Under Discussion
- target completion date
- 2026-07-21
New values
- current status
- Work In Progress
- target completion date
- 2026-07-31
Data source: Supabase
| taskId | PP-0144 |
|---|---|
| source | Commissioning Expert Addition |
| workstream | Utility |
| area | Utility Yard / Pilot Plant |
| equipmentSystem | Chilled Brine Plant |
| capacitySize | |
| activityCategory | Performance Test |
| readinessGate | Commissioning |
| activityDescription | Perform temperature achievement, circulation and load verification for chilled brine plant |
| currentStatus | Work In Progress |
| dashboardBucket | In Progress |
| priority | High |
| ownerDepartment | Vendor |
| responsiblePerson | Siva |
| vendorAgency | Utility Vendor |
| targetCompletionDate | 2026-07-31 |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Chilled Brine Plant commissioning completion |
| blocker | false |
| blockingImpactedItems | |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Performance trial report and utility handover. |
| remarksNextAction | date to be confirmed by vendor |
| lastUpdatedOn | 2026-07-28T12:07:20.717+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | No Target |
| completionPercent | 0.55 |
| criticalBlockerTheme |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: work under progress
Remarks: Added rewsponsible person
Remarks: date to be confirmed by vendor