PP-0146: Complete cooling tower fan rotation, circulation trial, make-up water and blowdown checks

Task Details

taskIdPP-0146
sourceCommissioning Expert Addition
workstreamUtility
areaUtility Yard / Pilot Plant
equipmentSystemCooling Towers
capacitySize
activityCategoryCommissioning
readinessGateCommissioning
activityDescriptionComplete cooling tower fan rotation, circulation trial, make-up water and blowdown checks
currentStatusWork In Progress
dashboardBucketIn Progress
priorityHigh
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji
vendorAgencyCooling Tower Vendor
targetCompletionDate2026-07-25
revisedTargetDate
actualCompletionDate
dependencyPredecessorElectrical power and water circulation readiness
blockerfalse
blockingImpactedItems
commissioningImpacttrue
qualificationImpactfalse
evidenceAcceptanceCriteriaCooling tower commissioning checklist signed.
remarksNextActionProcess cooling tower completed, vacuum cooling tower under progress
lastUpdatedOn2026-07-14T09:44:27.651+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0.55
criticalBlockerTheme

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 9:44 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Process cooling tower completed, vacuum cooling tower under progress

Old values

current status
Not Started
owner department
Engineering / Utility
responsible person
remarks next action
target completion date

New values

current status
Work In Progress
owner department
Engineering
responsible person
Mr.Sharma Ji
remarks next action
Process cooling tower completed, vacuum cooling tower under progress
target completion date
2026-07-25