Remarks: Hot water system received at site
Old values
- responsible person
- —
New values
- responsible person
- Amir Tanks
Data source: Supabase
| taskId | PP-0147 |
|---|---|
| source | Plant Head Email |
| workstream | Utility |
| area | Utility Yard / Pilot Plant |
| equipmentSystem | Hot Water System |
| capacitySize | |
| activityCategory | Receipt |
| readinessGate | Mechanical Completion |
| activityDescription | Verify hot water system received at site |
| currentStatus | Closed |
| dashboardBucket | Closed |
| priority | High |
| ownerDepartment | Engineering |
| responsiblePerson | Amir Tanks |
| vendorAgency | Amir Tanks |
| targetCompletionDate | |
| revisedTargetDate | |
| actualCompletionDate | 2026-07-03 |
| dependencyPredecessor | |
| blocker | false |
| blockingImpactedItems | |
| commissioningImpact | false |
| qualificationImpact | false |
| evidenceAcceptanceCriteria | Hot water system received. |
| remarksNextAction | |
| lastUpdatedOn | 2026-07-29T09:11:43.209+00:00 |
| updatedBy | Siva |
| daysToTarget | 0 |
| scheduleFlag | Closed |
| completionPercent | 1 |
| criticalBlockerTheme | Hot Water |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: Hot water system received at site