PP-0149: Complete hot water circulation pipeline connections and insulation

Task Details

taskIdPP-0149
sourceCommissioning Expert Addition
workstreamUtility
areaUtility Yard / Pilot Plant
equipmentSystemHot Water System
capacitySize
activityCategoryPiping / Utility
readinessGateUtility Completion
activityDescriptionComplete hot water circulation pipeline connections and insulation
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentEngineering
responsiblePersonMr.Sharma Ji
vendorAgencyAmir Tanks / Insulation Vendor
targetCompletionDate2026-07-28
revisedTargetDate
actualCompletionDate
dependencyPredecessorHot water system installation and insulation PO
blockertrue
blockingImpactedItemsReactor and VTD hot water connections
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaPiping completed, leak-tested and insulated.
remarksNextActioncompleted for Reactors, pipe line required for completion of VTD
lastUpdatedOn2026-07-14T10:15:56.142+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerThemeInsulation

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 14, 2026, 10:15 AMUpdated by: SivaSource: Stakeholder update form

Remarks: completed for Reactors, pipe line required for completion of VTD

Old values

current status
Not Started
responsible person
remarks next action
target completion date

New values

current status
Work In Progress
responsible person
Mr.Sharma Ji
remarks next action
completed for Reactors, pipe line required for completion of VTD
target completion date
2026-07-28