Remarks: to be done
Old values
- responsible person
- —
- target completion date
- —
New values
- responsible person
- Mr.Sharma Ji
- target completion date
- 2026-08-31
Data source: Supabase
| taskId | PP-0153 |
|---|---|
| source | Commissioning Expert Addition |
| workstream | Documentation |
| area | Pilot plant |
| equipmentSystem | Utility Manifold - SS Reactors |
| capacitySize | |
| activityCategory | Documentation |
| readinessGate | Documentation |
| activityDescription | Update as-built drawing for utility manifold - ss reactors |
| currentStatus | Not Started |
| dashboardBucket | Not Started |
| priority | High |
| ownerDepartment | Engineering |
| responsiblePerson | Mr.Sharma Ji |
| vendorAgency | Fabrication Vendor |
| targetCompletionDate | 2026-08-31 |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Final manifold installation and testing |
| blocker | false |
| blockingImpactedItems | |
| commissioningImpact | false |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Approved as-built drawing filed. |
| remarksNextAction | |
| lastUpdatedOn | 2026-07-31T08:43:23.999+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | No Target |
| completionPercent | 0 |
| criticalBlockerTheme |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: to be done