Remarks: to be done
Old values
- responsible person
- —
New values
- responsible person
- Mr.Sharma
Data source: Supabase
| taskId | PP-0159 |
|---|---|
| source | Commissioning Expert Addition |
| workstream | Documentation |
| area | Pilot plant |
| equipmentSystem | Utility Manifold - Clean Room Reactors |
| capacitySize | |
| activityCategory | Documentation |
| readinessGate | Documentation |
| activityDescription | Update as-built drawing for utility manifold - clean room reactors |
| currentStatus | Not Started |
| dashboardBucket | Not Started |
| priority | High |
| ownerDepartment | Engineering |
| responsiblePerson | Mr.Sharma |
| vendorAgency | Fabrication Vendor |
| targetCompletionDate | |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Final manifold installation and testing |
| blocker | false |
| blockingImpactedItems | |
| commissioningImpact | false |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Approved as-built drawing filed. |
| remarksNextAction | |
| lastUpdatedOn | 2026-07-31T08:46:21.16+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | No Target |
| completionPercent | 0 |
| criticalBlockerTheme |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: to be done