Remarks: Material received
Old values
- owner department
- Procurement
- responsible person
- —
New values
- owner department
- Engineering
- responsible person
- Mr.Sharma Ji
Data source: Supabase
| taskId | PP-0161 |
|---|---|
| source | Commissioning Expert Addition |
| workstream | Utility |
| area | Pilot plant |
| equipmentSystem | Low Vacuum System |
| capacitySize | |
| activityCategory | Procurement |
| readinessGate | Procurement |
| activityDescription | Issue PO and receive materials for low vacuum system |
| currentStatus | Closed |
| dashboardBucket | Closed |
| priority | Critical |
| ownerDepartment | Engineering |
| responsiblePerson | Mr.Sharma Ji |
| vendorAgency | Vacuum / Piping Vendor |
| targetCompletionDate | |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Low Vacuum System estimate and quote approval |
| blocker | true |
| blockingImpactedItems | Vacuum header installation |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | PO issued and material received. |
| remarksNextAction | |
| lastUpdatedOn | 2026-07-23T04:22:14.055+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 1 |
| criticalBlockerTheme | Vacuum |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: Material received
Remarks: Received