Remarks: work under progress
Old values
- current status
- Not Started
- responsible person
- —
- target completion date
- —
New values
- current status
- Work In Progress
- responsible person
- Mr.Sharma Ji / Vendor
- target completion date
- 2026-08-10
Data source: Supabase
| taskId | PP-0162 |
|---|---|
| source | Commissioning Expert Addition |
| workstream | Utility |
| area | Pilot plant |
| equipmentSystem | Low Vacuum System |
| capacitySize | |
| activityCategory | Installation |
| readinessGate | Utility Completion |
| activityDescription | Install low vacuum system piping, headers and equipment take-offs |
| currentStatus | Work In Progress |
| dashboardBucket | In Progress |
| priority | Critical |
| ownerDepartment | Engineering |
| responsiblePerson | Mr.Sharma Ji / Vendor |
| vendorAgency | Vacuum / Piping Vendor |
| targetCompletionDate | 2026-08-10 |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Low Vacuum System materials received |
| blocker | true |
| blockingImpactedItems | Vacuum hold tests for reactors and VTDs |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Installed and tagged piping with leak test record. |
| remarksNextAction | |
| lastUpdatedOn | 2026-07-23T04:25:25.943+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 0.55 |
| criticalBlockerTheme | Vacuum |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: work under progress