PP-0162: Install low vacuum system piping, headers and equipment take-offs
Task Details
| taskId | PP-0162 |
|---|---|
| source | Commissioning Expert Addition |
| workstream | Utility |
| area | Pilot plant |
| equipmentSystem | Low Vacuum System |
| capacitySize | |
| activityCategory | Installation |
| readinessGate | Utility Completion |
| activityDescription | Install low vacuum system piping, headers and equipment take-offs |
| currentStatus | Not Started |
| dashboardBucket | Not Started |
| priority | Critical |
| ownerDepartment | Engineering |
| responsiblePerson | |
| vendorAgency | Vacuum / Piping Vendor |
| targetCompletionDate | |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | Low Vacuum System materials received |
| blocker | true |
| blockingImpactedItems | Vacuum hold tests for reactors and VTDs |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Installed and tagged piping with leak test record. |
| remarksNextAction | |
| lastUpdatedOn | |
| updatedBy | |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 0 |
| criticalBlockerTheme | Vacuum |
Stakeholder Task Update
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Blocked By / Upstream Tasks
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
Blocking / Downstream Tasks
No downstream task dependencies are mapped for this task.
Recent Update History
No update history has been recorded for this task yet.