PP-0165: Issue PO and receive materials for high vacuum system

Task Details

taskIdPP-0165
sourceCommissioning Expert Addition
workstreamUtility
areaPilot plant
equipmentSystemHigh Vacuum System
capacitySize
activityCategoryProcurement
readinessGateProcurement
activityDescriptionIssue PO and receive materials for high vacuum system
currentStatusPO Under Process
dashboardBucketProcurement Pending
priorityCritical
ownerDepartmentProcurement
responsiblePerson
vendorAgencyVacuum / Piping Vendor
targetCompletionDate
revisedTargetDate
actualCompletionDate
dependencyPredecessorHigh Vacuum System estimate and quote approval
blockertrue
blockingImpactedItemsVacuum header installation
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaPO issued and material received.
remarksNextAction
lastUpdatedOn
updatedBy
daysToTarget
scheduleFlagBlocked
completionPercent0.2
criticalBlockerThemeVacuum

Stakeholder Task Update

Updates require DATA_SOURCE=supabase. CSV mode remains read-only.

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Update history is available when DATA_SOURCE=supabase is enabled. CSV mode remains read-only.