Remarks: After completion of piping work
Old values
- owner department
- Engineering / Utility
- responsible person
- —
- target completion date
- —
New values
- owner department
- Engineering
- responsible person
- Mr.Sharma Ji
- target completion date
- 2026-07-30
Data source: Supabase
| taskId | PP-0167 |
|---|---|
| source | Commissioning Expert Addition |
| workstream | Utility |
| area | Pilot plant |
| equipmentSystem | High Vacuum System |
| capacitySize | |
| activityCategory | Testing |
| readinessGate | Commissioning |
| activityDescription | Perform high vacuum system leak test and vacuum hold test |
| currentStatus | Not Started |
| dashboardBucket | Not Started |
| priority | Critical |
| ownerDepartment | Engineering |
| responsiblePerson | Mr.Sharma Ji |
| vendorAgency | Vacuum / Piping Vendor |
| targetCompletionDate | 2026-07-30 |
| revisedTargetDate | |
| actualCompletionDate | |
| dependencyPredecessor | High Vacuum System installation completion |
| blocker | true |
| blockingImpactedItems | Commissioning release for reactors and VTDs |
| commissioningImpact | true |
| qualificationImpact | true |
| evidenceAcceptanceCriteria | Vacuum hold test report and acceptance sign-off. |
| remarksNextAction | |
| lastUpdatedOn | 2026-07-14T10:12:40.192+00:00 |
| updatedBy | Siva |
| daysToTarget | |
| scheduleFlag | Blocked |
| completionPercent | 0 |
| criticalBlockerTheme | Vacuum |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: After completion of piping work