Remarks: work under progress
Old values
- current status
- Closed
- responsible person
- —
- target completion date
- —
New values
- current status
- Work In Progress
- responsible person
- Mr.Sharma / Amir Tanks
- target completion date
- 2026-08-14
Data source: Supabase
| taskId | PP-0168 |
|---|---|
| source | Plant Head Email |
| workstream | Safety / EHS |
| area | Pilot plant |
| equipmentSystem | Scrubber System |
| capacitySize | |
| activityCategory | Mechanical |
| readinessGate | Mechanical Completion |
| activityDescription | Verify scrubber installation completion |
| currentStatus | Work In Progress |
| dashboardBucket | In Progress |
| priority | High |
| ownerDepartment | Engineering / EHS |
| responsiblePerson | Mr.Sharma / Amir Tanks |
| vendorAgency | Scrubber Vendor |
| targetCompletionDate | 2026-08-14 |
| revisedTargetDate | |
| actualCompletionDate | 2026-07-03 |
| dependencyPredecessor | |
| blocker | false |
| blockingImpactedItems | |
| commissioningImpact | false |
| qualificationImpact | false |
| evidenceAcceptanceCriteria | Scrubber installation completed. |
| remarksNextAction | |
| lastUpdatedOn | 2026-07-27T11:25:03.746+00:00 |
| updatedBy | Siva |
| daysToTarget | 0 |
| scheduleFlag | Closed |
| completionPercent | 0.55 |
| criticalBlockerTheme | Scrubber |
No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.
Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.
No upstream task dependencies are mapped for this task.
No downstream task dependencies are mapped for this task.
Remarks: work under progress