PP-0170: Commission scrubber: circulation pump, blower/fan, media, drain and vent flow verification

Task Details

taskIdPP-0170
sourceCommissioning Expert Addition
workstreamSafety / EHS
areaPilot plant
equipmentSystemScrubber System
capacitySize
activityCategoryCommissioning
readinessGateCommissioning
activityDescriptionCommission scrubber: circulation pump, blower/fan, media, drain and vent flow verification
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentEngineering / EHS
responsiblePersonMr.Sharma / Vendor
vendorAgencyScrubber Vendor
targetCompletionDate2026-08-14
revisedTargetDate
actualCompletionDate
dependencyPredecessorScrubber piping completion and electrical readiness
blockertrue
blockingImpactedItemsSafe commissioning of reactors and VTDs
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaScrubber trial run report and EHS clearance.
remarksNextAction
lastUpdatedOn2026-07-27T11:26:35.408+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerThemeScrubber

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 27, 2026, 11:26 AMUpdated by: SivaSource: Stakeholder update form

Remarks: work under progress

Old values

current status
Not Started
responsible person
target completion date

New values

current status
Work In Progress
responsible person
Mr.Sharma / Vendor
target completion date
2026-08-14