PP-0171: Prepare scrubber operating SOP, emergency response logic and maintenance checklist

Task Details

taskIdPP-0171
sourceCommissioning Expert Addition
workstreamDocumentation
areaPilot plant
equipmentSystemScrubber System
capacitySize
activityCategoryDocumentation
readinessGateDocumentation
activityDescriptionPrepare scrubber operating SOP, emergency response logic and maintenance checklist
currentStatusNot Started
dashboardBucketNot Started
priorityHigh
ownerDepartmentEHS / Production / QA
responsiblePersonMr.Jain
vendorAgency
targetCompletionDate2026-08-31
revisedTargetDate
actualCompletionDate
dependencyPredecessorScrubber design and commissioning checklist
blockerfalse
blockingImpactedItems
commissioningImpactfalse
qualificationImpacttrue
evidenceAcceptanceCriteriaApproved SOP and EHS training record.
remarksNextAction
lastUpdatedOn2026-07-27T11:27:38.918+00:00
updatedBySiva
daysToTarget
scheduleFlagNo Target
completionPercent0
criticalBlockerThemeScrubber

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 27, 2026, 11:27 AMUpdated by: SivaSource: Stakeholder update form

Remarks: SOP to be prepared after completion of installation & commissioning

Old values

responsible person
target completion date

New values

responsible person
Mr.Jain
target completion date
2026-08-31