PP-0172: Complete HVAC ducting work in clean room

Task Details

taskIdPP-0172
sourcePlant Head Email / Commissioning Addition
workstreamHVAC / Clean Room
areaClean room
equipmentSystemHVAC System
capacitySize
activityCategoryHVAC / Clean Room
readinessGateArea Readiness
activityDescriptionComplete HVAC ducting work in clean room
currentStatusWork In Progress
dashboardBucketIn Progress
priorityCritical
ownerDepartmentVendor
responsiblePersonPradham HVAC
vendorAgencyHVAC Vendor
targetCompletionDate2026-08-05
revisedTargetDate
actualCompletionDate
dependencyPredecessorHVAC ducting completion
blockertrue
blockingImpactedItemsCeiling closure and clean room readiness
commissioningImpacttrue
qualificationImpacttrue
evidenceAcceptanceCriteriaHVAC/clean room verification record and QA/EHS sign-off.
remarksNextActionCeiling work to be started from 20/07/2026, after completion of ceiling work HVAC ducting work to be continued
lastUpdatedOn2026-07-17T10:59:26.793+00:00
updatedBySiva
daysToTarget
scheduleFlagBlocked
completionPercent0.55
criticalBlockerThemeHVAC

Stakeholder Task Update

No login is required for this pilot flow. Updates are submitted to server-side Supabase operations only and each saved change creates a task_updates audit row.

Blocked By / Upstream Tasks

Dependency-blocked status is derived from predecessor task completion and is separate from the manual blocker flag.

No upstream task dependencies are mapped for this task.

Blocking / Downstream Tasks

No downstream task dependencies are mapped for this task.

Recent Update History

Jul 17, 2026, 10:59 AMUpdated by: SivaSource: Stakeholder update form

Remarks: Ceiling work to be started from 20/07/2026, after completion of ceiling work HVAC ducting work to be continued

Old values

owner department
Engineering / HVAC
responsible person
remarks next action
target completion date

New values

owner department
Vendor
responsible person
Pradham HVAC
remarks next action
Ceiling work to be started from 20/07/2026, after completion of ceiling work HVAC ducting work to be continued
target completion date
2026-08-05